The PRINCE2 PRINCE2-Agile-Foundation exam covers topics such as the PRINCE2 principles, themes, and processes, as well as Agile concepts such as Scrum, Kanban, and Lean. PRINCE2-Agile-Foundation exam also tests the candidate's understanding of how to apply Agile practices within the PRINCE2 framework and how to tailor PRINCE2 to suit different project environments. PRINCE2-Agile-Foundation exam has a total of 50 questions, and the passing score is 55%.

 

NEW QUESTION # 42
Which statement describes how the PRINCE2 'starting up a project' process can be applied in an agile environment?

  • A. PRINCE2 requires a lengthy start to a project
  • B. PRINCE2 is predictive, but not emergent
  • C. PRINCE2 requires a disruptive start to a project
  • D. PRINCE2 is predictive and can be emergent

Answer: D


NEW QUESTION # 43
What information is NOT typically displayed on a burn chart?

  • A. Amount of time elapsed
  • B. Definition of 'ready'
  • C. Effort remaining
  • D. Actual amount of work done

Answer: B


NEW QUESTION # 44
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?

  • A. Using email to document discussions
  • B. Using visualization to display information
  • C. Using social media to reach more people
  • D. Using meeting minutes to share decisions

Answer: B


NEW QUESTION # 45
Which is a key objective of running a workshop?

  • A. To communicate decisions to the wider stakeholder community
  • B. To make day-to-day decisions on behalf of the delivery team within a sprint
  • C. To make daily progress visible to the delivery team and key stakeholders
  • D. To encourage collaboration and create the defined outputs from the event

Answer: D


NEW QUESTION # 46
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

  • A. It should always be carried out informally
  • B. It should always be appropriate to the needs of the project
  • C. It should always be addressed during the daily stand-ups
  • D. It should always be carried out formally

Answer: B


NEW QUESTION # 47
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should increase the stage-level time tolerance
  • B. The project board should make decisions based on the Agilometer risks
  • C. The project board should attend regular project progress meetings
  • D. A project board member should fulfill the product owner role within a delivery team

Answer: D


NEW QUESTION # 48
Which is a typical characteristic of 'business as usual' work?

  • A. It is executed by program management
  • B. It requires a specific dedicated project manager
  • C. It is delivered by a temporary team
  • D. It is delivered by an established team

Answer: D


NEW QUESTION # 49
When creating the project product description, how should the purpose of the project product be defined?

  • A. As a vision
  • B. As an opportunity
  • C. As a goal
  • D. As an outcome

Answer: D


NEW QUESTION # 50
Which BEST describes the senior user role when tailoring the organization theme?

  • A. A 'coach'
  • B. A 'super product owner'
  • C. An 'executive sponsor'
  • D. An 'agile sponsor'

Answer: B


NEW QUESTION # 51
Which statement describes the Kanban approach?

  • A. It is an iterative timeboxed approach that helps teams generate value
  • B. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
  • C. It is used to make system improvements using visualization and by controlling work in progress
  • D. It was originally focused in creating new companies and is now used to speed up product delivery

Answer: C


NEW QUESTION # 52
What is the MOST LIKELY benefit from frequent releases into operational use?

  • A. The risks associated with agile ways of working are assessed
  • B. The need for customer involvement is increased
  • C. Feedback is obtained from real customers
  • D. The need for configuration management is reduced

Answer: C


NEW QUESTION # 53
How does the change theme regard change in PRINCE2 Agile?

  • A. As inevitable
  • B. As something to be avoided
  • C. As a necessity
  • D. As disruptive

Answer: A


NEW QUESTION # 54
When should PRINCE2 Agile be used?

  • A. When an established team performs product maintenance
  • B. When a team is created to deliver a specific product
  • C. When delivering an ongoing service to a customer
  • D. When simple requests to update a product are implemented

Answer: A


NEW QUESTION # 55
What is typically displayed on a board to show progress to people working on a project?

  • A. Information radiator
  • B. Product backlog
  • C. User story
  • D. Agilometer assessment

Answer: A


NEW QUESTION # 56
Which statement about quality tolerances for a product is CORRECT in an agile context?

  • A. All quality criteria should have zero tolerance
  • B. All quality criteria tolerance must be fixed
  • C. Setting quality tolerance relies on prioritising quality criteria
  • D. Quality tolerances should be the same for all quality criteria

Answer: C


NEW QUESTION # 57
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

  • A. It enables team dynamics to remain the same
  • B. It improves the supplier's reputation with the customer
  • C. It sets the project baseline at the correct level
  • D. It reduces testing in order to meet deadlines

Answer: D


NEW QUESTION # 58
What needs to happen when new detailed requirements are added to a timebox?

  • A. The delivery milestones should be reviewed and re-planned
  • B. Requirements of a similar level of effort should be removed
  • C. Formal change control should be applied
  • D. More people should be added to the delivery team

Answer: B


NEW QUESTION # 59
Who needs to be aware that flexing what is delivered may affect the expected benefits of the project?

  • A. Customer subject matter expert and the supplier representative
  • B. The team quality assurance and project support
  • C. The project manager and the project board
  • D. The team manager and the senior supplier

Answer: C


NEW QUESTION # 60
Which statement about the waterfall methodology definition is CORRECT?

  • A. It prevents earlier phases of development being revisited
  • B. It focuses on responding to changing requirements
  • C. It uses an iterative and incremental approach
  • D. It delivers products more frequently in shorter phases

Answer: A


NEW QUESTION # 61
Which should be an objective of a retrospective?

  • A. To identify key process improvements to implement in the next sprint
  • B. To focus on objective learning rather than subjective feelings and emotions
  • C. To encourage the team to bond by allowing social activities to take place
  • D. To identify many process improvements and implement them

Answer: A


NEW QUESTION # 62
In Scrum, what answers the question 'what can be done this sprint?'

  • A. Sprint planning
  • B. Sprint review
  • C. Daily scrum
  • D. Increment

Answer: C


NEW QUESTION # 63
......