The PRINCE2 PRINCE2-Agile-Foundation exam covers topics such as the PRINCE2 principles, themes, and processes, as well as Agile concepts such as Scrum, Kanban, and Lean. PRINCE2-Agile-Foundation exam also tests the candidate's understanding of how to apply Agile practices within the PRINCE2 framework and how to tailor PRINCE2 to suit different project environments. PRINCE2-Agile-Foundation exam has a total of 50 questions, and the passing score is 55%.
NEW QUESTION # 42
Which statement describes how the PRINCE2 'starting up a project' process can be applied in an agile environment?
- A. PRINCE2 requires a lengthy start to a project
- B. PRINCE2 is predictive, but not emergent
- C. PRINCE2 requires a disruptive start to a project
- D. PRINCE2 is predictive and can be emergent
Answer: D
NEW QUESTION # 43
What information is NOT typically displayed on a burn chart?
- A. Amount of time elapsed
- B. Definition of 'ready'
- C. Effort remaining
- D. Actual amount of work done
Answer: B
NEW QUESTION # 44
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using email to document discussions
- B. Using visualization to display information
- C. Using social media to reach more people
- D. Using meeting minutes to share decisions
Answer: B
NEW QUESTION # 45
Which is a key objective of running a workshop?
- A. To communicate decisions to the wider stakeholder community
- B. To make day-to-day decisions on behalf of the delivery team within a sprint
- C. To make daily progress visible to the delivery team and key stakeholders
- D. To encourage collaboration and create the defined outputs from the event
Answer: D
NEW QUESTION # 46
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?
- A. It should always be carried out informally
- B. It should always be appropriate to the needs of the project
- C. It should always be addressed during the daily stand-ups
- D. It should always be carried out formally
Answer: B
NEW QUESTION # 47
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should increase the stage-level time tolerance
- B. The project board should make decisions based on the Agilometer risks
- C. The project board should attend regular project progress meetings
- D. A project board member should fulfill the product owner role within a delivery team
Answer: D
NEW QUESTION # 48
Which is a typical characteristic of 'business as usual' work?
- A. It is executed by program management
- B. It requires a specific dedicated project manager
- C. It is delivered by a temporary team
- D. It is delivered by an established team
Answer: D
NEW QUESTION # 49
When creating the project product description, how should the purpose of the project product be defined?
- A. As a vision
- B. As an opportunity
- C. As a goal
- D. As an outcome
Answer: D
NEW QUESTION # 50
Which BEST describes the senior user role when tailoring the organization theme?
- A. A 'coach'
- B. A 'super product owner'
- C. An 'executive sponsor'
- D. An 'agile sponsor'
Answer: B
NEW QUESTION # 51
Which statement describes the Kanban approach?
- A. It is an iterative timeboxed approach that helps teams generate value
- B. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
- C. It is used to make system improvements using visualization and by controlling work in progress
- D. It was originally focused in creating new companies and is now used to speed up product delivery
Answer: C
NEW QUESTION # 52
What is the MOST LIKELY benefit from frequent releases into operational use?
- A. The risks associated with agile ways of working are assessed
- B. The need for customer involvement is increased
- C. Feedback is obtained from real customers
- D. The need for configuration management is reduced
Answer: C
NEW QUESTION # 53
How does the change theme regard change in PRINCE2 Agile?
- A. As inevitable
- B. As something to be avoided
- C. As a necessity
- D. As disruptive
Answer: A
NEW QUESTION # 54
When should PRINCE2 Agile be used?
- A. When an established team performs product maintenance
- B. When a team is created to deliver a specific product
- C. When delivering an ongoing service to a customer
- D. When simple requests to update a product are implemented
Answer: A
NEW QUESTION # 55
What is typically displayed on a board to show progress to people working on a project?
- A. Information radiator
- B. Product backlog
- C. User story
- D. Agilometer assessment
Answer: A
NEW QUESTION # 56
Which statement about quality tolerances for a product is CORRECT in an agile context?
- A. All quality criteria should have zero tolerance
- B. All quality criteria tolerance must be fixed
- C. Setting quality tolerance relies on prioritising quality criteria
- D. Quality tolerances should be the same for all quality criteria
Answer: C
NEW QUESTION # 57
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?
- A. It enables team dynamics to remain the same
- B. It improves the supplier's reputation with the customer
- C. It sets the project baseline at the correct level
- D. It reduces testing in order to meet deadlines
Answer: D
NEW QUESTION # 58
What needs to happen when new detailed requirements are added to a timebox?
- A. The delivery milestones should be reviewed and re-planned
- B. Requirements of a similar level of effort should be removed
- C. Formal change control should be applied
- D. More people should be added to the delivery team
Answer: B
NEW QUESTION # 59
Who needs to be aware that flexing what is delivered may affect the expected benefits of the project?
- A. Customer subject matter expert and the supplier representative
- B. The team quality assurance and project support
- C. The project manager and the project board
- D. The team manager and the senior supplier
Answer: C
NEW QUESTION # 60
Which statement about the waterfall methodology definition is CORRECT?
- A. It prevents earlier phases of development being revisited
- B. It focuses on responding to changing requirements
- C. It uses an iterative and incremental approach
- D. It delivers products more frequently in shorter phases
Answer: A
NEW QUESTION # 61
Which should be an objective of a retrospective?
- A. To identify key process improvements to implement in the next sprint
- B. To focus on objective learning rather than subjective feelings and emotions
- C. To encourage the team to bond by allowing social activities to take place
- D. To identify many process improvements and implement them
Answer: A
NEW QUESTION # 62
In Scrum, what answers the question 'what can be done this sprint?'
- A. Sprint planning
- B. Sprint review
- C. Daily scrum
- D. Increment
Answer: C
NEW QUESTION # 63
......